Previously, when you clicked 100% to set a task complete, GamePlan assumed the task was finished on schedule. If the task did not finish on schedule, you clicked Edit Timesheet and entered when the task was worked on.
Now when you click 100% you can specify when the task finished.
The default is On schedule. Click OK and this works the same as before. The timesheet is automatically created showing the task finishing on schedule.
If the task was just finished, click Now and then OK. The finish time rounds to the most recent 15 minute interval and the timesheet is automatically created. The schedule for all downstream tasks adjusts accordingly.
A third option, Date/time, lets you enter the exact date and time that the task started and finished. The timesheet is automatically created and the schedule for all downstream tasks adjusts accordingly.
This new functionality gives you an easy way to keep your schedule valid and up to date without having to manually enter timesheets.
Subscribe To Our Newsletter
Get updates and learn from the best
More To Explore
The Purpose & Benefits of Gantt Charts in Project Management
Gantt charts are like the hit Korean drama Squid Game–people either love it or hate it (because they don’t get it). Moreover, research indicates that Gantt Charts
The Ultimate Guide to Visual Project Management Software
Projects today no longer follow a linear path primarily because projects have become exceedingly data-rich (think: data related to labor estimates, capital costs, operational expenses,